Geotechnical report complete
The geotechnical report confirms that the slope has experienced slumping and movement dating back to at least 1975. The report shows the existing crack in the slope predates recent vegetation removal.
The report also reveals complexities that weren’t identified in the original remediation back in 2024.
Causes identified in report
- Subsurface soil conditions: The site has a unique subsurface soil profile with properties that reduce the natural stability of the slope.
- Groundwater influence: Trapped groundwater in the cut slope is pushing up pore pressures and weakening the slope.
- Surface water and stormwater impacts: Surface flows from rainfall on the slope and stormwater discharge from upstream properties is entering the slope area and affecting soil strength and stability.
The report confirms that replanting the area at this stage would not resolve the issue, the underlying groundwater problems must be addressed first.
Remediation options
Three remediation options have been outlined in the report. Council officers are now seeking further information on each, including detailed costs estimates, as we look to find the safest, most cost effective long-term solution.
We're also investigating funding options (from other levels of government) as early indications suggest the works may cost around $3 million.
Securing government assistance may take some time. Now officers have better information on the likely causes we have begun to seek help.
Next steps
Council officers are preparing a summary of the final report to simplify its technical nature and support community understanding.
The complex nature of the issues revealed by the geotechnical report, and the expected cost of remediation, means it is now unlikely any on-ground works on a long-term fix will take place before late 2026 at the earliest.
We know locals care deeply about the look of the slope due to its prominence, so we’ll discuss with Aireys Inlet & District Association once the best solution has been identified. This will help us test how best to blend the works into the landscape. However, it’s important that the long-term stability and safety of the slope is prioritised.
Due to the nature of the slope and embankment the Fairhaven slip is a highly complex problem - and our focus is on delivering a safe, long-term fix.
We know the process is taking time and we appreciate the community’s continued patience and understanding as we work toward a long-term solution.
Monitoring and safety
Geotechnical consultants continue to monitor the whole area, including the properties above the landslip. Monitoring to date shows no ground movement above the visible cracks, meaning no current risk to these properties.
The two-way traffic diversion will remain in place through the peak holiday period and until remediation works are completed to ensure community safety.